Although it may not feel this way, the DDC Street Improvement Project is on schedule and 90% done. However, the DDC (city agency) and Halcyon (the contractor) want to emphasize that the delays are almost entirely due to issues with Con Ed.
The street lights on Water and Jay have been out because Con Ed had to switch off electricity and left them dark. When we made them aware, Halcyon sent a crew out to light them temporarily.
Below is a list of what is complete and ready for underground work on Water Street, Jay to Bridge, with all underground utilities complete for the entire contract by April/May 2025.
Major Tasks
Gas relocation - complete
Electric relocation - complete
Sanitary sewer replacement - complete
Distribution water main replacement - complete
Large steel trunk water main installation - complete
New storm sewer along north curb line & catch basins - ongoing, should be complete by March 2025.
Two small sidewalk vaults for 69 Jay to fill in - should be complete by late January 2025.
Final curb, sidewalk, cobblestone street restoration and Plaza pavers for below locations should start around April 1, 2025 and be complete around Thanksgiving 2025.
Water, Bridge to Pearl
Jay, John to Water