DDC Street Project Update

Writer's picture: ElisaElisa

Updated: Dec 4, 2024


Although it may not feel this way, the DDC Street Improvement Project is on schedule and 90% done. However, the DDC (city agency) and Halcyon (the contractor) want to emphasize that the delays are almost entirely due to issues with Con Ed.


The street lights on Water and Jay have been out because Con Ed had to switch off electricity and left them dark. When we made them aware, Halcyon sent a crew out to light them temporarily.


Below is a list of what is complete and ready for underground work on Water Street, Jay to Bridge, with all underground utilities complete for the entire contract by April/May 2025.


Major Tasks

  1. Gas relocation - complete

  2. Electric relocation - complete

  3. Sanitary sewer replacement - complete

  4. Distribution water main replacement - complete

  5. Large steel trunk water main installation - complete

  6. New storm sewer along north curb line & catch basins - ongoing, should be complete by March 2025.

  7. Two small sidewalk vaults for 69 Jay to fill in - should be complete by late January 2025.


Final curb, sidewalk, cobblestone street restoration and Plaza pavers for below locations should start around April 1, 2025 and be complete around Thanksgiving 2025. 


  1.     Water, Bridge to Pearl

  2.     Jay, John to Water

12 views0 comments